WO-4489 · Fieldstone Construction
Mezzanine + access stair
Burnley unit — phase 2 · qty 1 · S355 UB + plate
due Fri 22 Aug
Revision-locked · Drawing NGF-4489, Rev B. Only the current rev can be issued to the floor.Rev A superseded
Progress
42%
Hours est / act
180 / 96
Job value
£21,800
Exec class
EXC3 · EN 1090
Routing · digital traveller9 operations
OP 10Programme / nestDone
Programming / Nest · Lantek + Inventor (read)Gary Holtest 10h · act 10.5h ▲
OP 20Laser cut plateDone
Fibre Laser · Morgan RushworthMick Bardsleyest 20h · act 21h ▲
OP 30BendDone
Press Brake · Amada 100-tonDave Sutcliffeest 16h · act 20h ▲
OP 40Fit-up / tackRunning
Fit-up Bay · Fitting benchNathan Kirk · on nowest 40h
OP 50Weld to WPSQueued
Weld Bay 1 · MIG/MMA bay
Waiting on kit — not all parts at the bay yet
OP 60Linish / deburrQueued
Finishing · Linish + paint booth
OP 70Galvanise (subbed)Queued
Galvanising (sub)
OP 80QC first-offQueued
Inspection · QC bench
OP 90Dispatch / installQueued
Dispatch / Install · Yard + install team
Every line here was a scan at the kiosk — badge → job → operation. Nobody walked the floor or totted hours on a scrap of paper.