Insight · capacity & promise dates

Capacity & Promising

What's committed on every machine, where the queue really is, and the delivery date you can promise without guessing.

Committed on the floor
352h
remaining, all live jobs
The constraint
Weld Bay 1
2.5 weeks deep
Earliest start
13 days
to clear the queue behind it
Centres over 1 wk
3
of 11 work centres
Forward load by work centrecommitted hrs vs capacity · 4-wk horizon

Each bar is the hours already committed, against that centre's weekly capacity. Anything past 1 week is where promises slip.

Weld Bay 1
101.5h / 40h wk
2.5 wk
Finishing
58.8h / 40h wk
1.5 wk
Dispatch / Install
56h / 40h wk
1.4 wk
Weld Bay 2
37h / 40h wk
0.9 wk
Inspection
32h / 40h wk
0.8 wk
Programming / Nest
26h / 40h wk
0.7 wk
Fit-up Bay
29h / 80h wk
0.4 wk
Fibre Laser
12h / 45h wk
0.3 wk
Tube Laser
0h / 40h wk
0 wk
Plasma
0h / 40h wk
0 wk
Press Brake
0h / 40h wk
0 wk
under a week1–2 weeks2 weeks+gridlines = 1 / 2 / 3 wk