Job Costing

Quoted hours vs the hours you actually burned — per job, per operation. The jobs quietly losing money stop being a mystery.

Unplanned hours this week

Every hour over quote is margin walking out the door. Set your shop rate — see the bill.

£1,716
33h over quote · 4 jobs
52
Blended shop rate — edit it and every job below re-costs. Labour only; material and sub-contract sit on their own lines.
Ran at a lossWO-4463 · Delta Fabrication
Bracket batch (repeat)
Quoted
30h
£3,300
Actual
38h
£3,910
Margin left
£990
was £1,600
Quoted 30h, ran 38h£610 gone. It's a repeat — re-quote it before you run it again.
Every job · quoted vs actuallive from the floor clocks
WOJob / customerHours q / aCost q / aMarginFlag
WO-4471
External steel staircase
Kingsway Construction
128 / 141 ▲13£9,900 / £11,12025%Over quote
WO-4468
Powder-coated handrail run
Ribdale County Council
96 / 88 ▼8£5,600 / £5,24038%On / under
WO-4482
Laser-cut bracket batch
Delta Fabrication
22 / 19 ▼3£2,100 / £1,88040%On / underre-quote
WO-4475
Stainless balcony + glass balustrade
Private · Mr Ashworth
84 / 61 ▼23£7,400 / £5,30053%On / under
WO-4479
Driveway gates (pair)
Private · Mrs Kenyon
54 / 30 ▼24£3,050 / £1,72063%On / under
WO-4460
Mezzanine handrail frame
Fieldstone Construction
60 / 58 ▼2£4,050 / £4,01036%On / under
WO-4463
Bracket batch (repeat)
Delta Fabrication
30 / 38 ▲8£3,300 / £3,91020%Over quotere-quote
WO-4489
Mezzanine + access stair
Fieldstone Construction
180 / 96 ▼84£14,200 / £7,60065%On / under
WO-4486
Goods-lift shaft frame
Kingsway Construction
140 / 132 ▼8£9,900 / £9,40039%On / under
WO-4472
Wall-mounted handrail (×8)
Ribdale County Council
46 / 44 ▼2£3,200 / £3,05041%On / under
WO-4455
Steel walkway + handrail
Northmoor Civils
110 / 116 ▲6£8,200 / £8,60032%Over quote
WO-4451
Plant machinery guards (set)
Delta Fabrication
40 / 37 ▼3£3,400 / £3,20041%On / under
WO-4448
Skip / bin store enclosure
Private · Mr Partington
34 / 40 ▲6£2,500 / £2,82026%Over quote
Where the hours wentWO-4471 · external steel staircase+13h vs quote

Not a mystery overrun — the terminal shows exactly which operation ate the hours. The brake set-up is the tax.

Bend treads
Press Brake · 4.5h set-up
12h → 19.3h ▲7.3
Laser cut stringers/treads
Fibre Laser
14h → 16.7h ▲2.7
Programme / nest
Programming / Nest
6h → 7h ▲1
Plasma cut base plates 40mm
Plasma
5h → 5.6h ▲0.6
Fit-up / tack
Fit-up Bay
20h → 14h