WO-4460 · Fieldstone Construction
Mezzanine handrail frame
Burnley unit fit-out · qty 1 · 40×40 SHS tube
due Tue 5 Aug
Revision-locked · Drawing NGF-4460, Rev B. Only the current rev can be issued to the floor.Rev A superseded
Progress
88%
Hours est / act
60 / 58
Job value
£6,300
Exec class
EXC2 · EN 1090
Routing · digital traveller7 operations
OP 10Programme / nestDone
Programming / Nest · Lantek + Inventor (read)Gary Holtest 3h · act 3.2h ▲
OP 20Tube laserDone
Tube Laser · RVD tube laserMick Bardsleyest 8h · act 8.6h ▲
OP 30Fit-upDone
Fit-up Bay · Fitting benchTom Pillingest 14h · act 15h ▲
OP 40WeldDone
Weld Bay 1 · MIG/MMA bayAndy Kershawest 22h · act 21.5h
OP 50LinishDone
Finishing · Linish + paint boothJosh Crookest 8h · act 8h
OP 60QC first-offRunning
Inspection · QC benchWilliam Hunt · on nowest 3h
OP 70DispatchQueued
Dispatch / Install · Yard + install team
Every line here was a scan at the kiosk — badge → job → operation. Nobody walked the floor or totted hours on a scrap of paper.